PeterM and BB just accomplished their tasks last evening, Thursday, July 31st, 2014. They are on the way to Airport to return to Melbourne (Australia).
Three weeks working on different tasks – now, Mission ACCOMPLISHED!
Take a look at tasks they’ve fulfilled:

1. AUS Container – unloaded complete.

2. School facility
a. lockers – mounted √
b. benches and tables – manufactured and painted – √
c. one class-room – all furniture and study sets – mounted – √
d. textbook boards for teachers – mounted √

07_lockers  Textbookboards teached 0714_01

3. Orphanage Dormitories
a. Suit boards in all 11 dormitories – mounted √
b. All suitboards sealed with silicon waterproved agent – √
c. Doors to dormitories, inclusive frames and architraves – all mounted and paint with primer √

4. Campus surroundings
a. Electrical generator 10kVA – concrete foundation √; multiple outside sockets for electrical devices – √
b. Outwards walls – re-painted within homogenous colour – PEANUT WEATHER GUARD √

Campus_newpaint01

c. Rainwater collection system – four pipelines installed into inner courtyard √; pipeline to kitchen area – mounted √ ;
d. Inner courtyard – roof; foundation for pillars – done √; addings for mettalic connectors to actual campus roof – installed √
e. Chicken “house” – plywood door installed √; plasticgrid to windows – mounted √.

Rainwater colect_01

 